Analysis of the Assessment of Loess Tunnel Settlement before Laying Slab Track on Zhengzhou-Xi'an Passenger Dedicated Line |
GAO Shu-feng |
TheThird Railway Survey and Design InstituteGroup Corporation, Tianjin 300251, China |
|
|
Abstract Research purposes:Zhengzhou-Xia' n PassengerDedicated Line is the first long railway line adopting the modified Zueblin slab track with bi-block sleepers on the whole line in China, whereas the slab track requires less subsidence for its foundation. However, for the subsidence of loess tunnels, there is nomature experience for reference athome and abroad and for the assessmentof tunnel foundation subsidence, even no example is available before. This paper attempts to improve the assessmentprocedure and summarize some laws of the tunnel foundation subsidence based on the analysis and study on the tunnel assessment forZhengzhou-Xia' n PassengerDedicated Line.
Research conclusions:The analyses show the total tunnel foundation subsidence is very smal,l most less than 5mm and onlymeasured data from a few of cross sections can offer a reasonable regression curve whilemost of sections can no,t and the tunnel deformation tends to be stable in 60~120 days after finishing the secondary lining.
|
Received: 17 November 2008
|
|
|
|
|
[1] 铁建设[2006]158号,客运专线无碴轨道铺设条件评估 技术指南[S].
[2] 中铁第一勘察设计院集团有限公司.高桥隧道及潼洛川 隧道基础沉降报告[R].西安:中铁第一勘察设计院集 团有限公司, 2008.
[3] 铁建设[2007]47号,新建时速300~350公里客运专线 铁路设计暂行规定[S].
|
|
|
|