Comprehensive Route Design on Geology and Risk of Yuxi to Mohan Railway |
YU Ling-kun |
Kunming Branch of China Railway Eryuan Engineering Group Co. Ltd,Kunming,Yunnan 650200,China |
|
|
Abstract Research purposes: With the construction of a large number of railway in our country,especially in dangerous mountains,it increases the risk of construction. The source of risk control is the design. After many years of development,the railway design pays more attention to the engineering safety,reliability,low risk and economy. This paper summarizes the previous route design work of Yuxi to Mohan railway,then puts forward the concept of route design idea of each design stage.
Research conclusions:(1)Yuxi to Mohan railway landform undulates terribly,geological conditions are complicated, risk is higher. With the comprehensive comparison of lots of schemes,make the route through the hot springs low temperature zone,the influence of active faults is small,tunnel risk is reduced greatly,and a solid foundation for the future design is laid. (2)Different railway projects has the different risk of route design. According to the principle of route design that risk should be analyzed,from the analysis of the design process,the comprehensive route design on geology and risk in pre-feasibility phases is dominated by macro analysis,the route selection principle of significant risk should be dominated by regional geological data and site reconnaissance situation,thus instruct route selection design. Based on further investigation on the geological conditions,the major geological risk should be verified in feasibility phases,the geological special research is carried out when necessary,engineering measures should be implemented in the preliminary design and construction drawing phases.(3)This research has a certain reference significance for other high-risk railway projects.
|
Received: 27 January 2014
|
|
|
|
|
[1]黄海涌,邵军义,康莹.我国建筑施工企业融资能力研究 [J].建筑经济,2008(S2);8-10.
Huang Haiyong, Shao Junyi, Kangying. Research on the Financing Capacity of National Construction Enterprises.[J].Construction Economy, 2008(S2): 8-10.
[2]韩晶.工程投融资建设模式回购风险与控制策略分析 [J].铁道工程学报,2014(5):106-109.
Han Jing. Analysis of Repurchase Risk and Control Strategies of Project Investment and Financing Constouction Mode [ J].Journal of Railway Engineering Society, 2014(5);106-109.
[3]中国中铁.探索产融结合模式推进成都BT项目建设侧记 [N/OL].中国中铁股份有限公司青年网,2014 - 02 – 24.
http;//www. Crecyouth.com/portal/Navigate/Article. Aspx? id =32448.
Sidelights on Chengdu BT Projects by the Industry- In"nancing Mode [ N/OL.CRECYOUTH, 2014-02-24. http;//www.crecyouth.com/portal/Navigate/Article. Aspx? id = 32448.
[4]高妮.我国大型建筑企业融资方式研究[D].北京:北京交通大学,2011.
Gao Ni. Research on the Financing Models of Large- scale Construction Enterprises[D].Beijing; Beijing Jiaotong University, 2011.
|
|
|
|