Research on the Construction Quality Evaluation System of High Speed Railway CRTS II Slab Ballastless |
MA Ming-zheng1,XU Jin-hui1,WANG Biao WANG Ping1,MEI Zhi-shan2 |
1 .Southwest Jiaotong Group Co. Ltd,Wuhan, University, Chengdu,Sichuan 610031,China; 2. China Railway Siyuan Survey and Design Hubei 430063,China |
|
|
Abstract Research purposes: The evaluation for high speed railway ballasts track construction quality management means doing comprehensive evaluation for the quality management level of high speed railway construction projects. Scientific and reasonable evaluation is conductive to the development and perfect of high speed railway ballastless track construction quality management. Based on the field test data and combining the high speed ballast less track features, this paper uses the analysis hierarchy process and fuzzy comprehensive evaluation of system engineering to build a scientific and effective quality evaluation system of high speed railway ballastless track construction quality.
Research conclusions ;(1)The paper builds the quality evaluation system of high speed railway CRTS ballast less track by combining the analysis hierarchy process with fuzzy comprehensive evaluation.(2)The established quality evaluation system is used in a section with CRTS B ballastless track, and the construction quality is proved good. (3)The research results provide an evaluation basis for the high speed railway ballastless track construction quality, and will promote the scientific implementation of China high speed railway ballastless track construction quality management.
|
Received: 09 December 2013
|
|
|
|
|
[1]何华武.无碴轨道技术[M].北京:中国铁道出版社, 2005.
He Huawu. T'he Technology of Ballastless Track[M]. Beijing : China Railway Publishing House , 2005.
[2]刘学毅,赵坪瑞,杨荣山,等.客运专线无砟轨道设计理论与方法[M].成都:西南交通大学出版社,2010.
Liu Xueyi , Zhao Pingrui , Yang Rongshan , etc. Design Theory and Methods of Ballastless Track of Passenger Dedicated Line[M].Chengdu ; Southwest Jiaotong University Press, 2010.
[3]赵国堂.高速铁路无砟轨道结构[M].北京:中国铁道出版社,2006.
Zhao Guotang. The Structure of Ballistics Track of High-speed Railway[M].Beijing; China Railway Publishing House , 2006.
[4]朱高明.国内外无砟轨道的研究与应用综述「J].铁道 工程学报,2008(7):28-30.
Zhu Gaoming. Overall Comments on Study and Application of Ballastess Track at Home and Abroad [ J ] . Journal of Railway Engineering Society , 2008 (7 ): 28-30.
[5]肖杰灵,刘学毅,杨荣山.无砟轨道系统功能设计的概 念与内涵[J].铁道工程学报,2008 (3) :20 - 23.
Xiao Jieling , Liu Xueyi , Yang Rongshan. Concept and Intension on System Function Design of Ballastiess Track[J].Journal of Railway Engineering Society, 2008{3):20-23.
[6]陈小平,王平,陈嵘.弹性支承块式无碑轨道的减振机 理[J],铁道学报,2007(5);69-72.
Chen Xiaoping, Wang Ping, Chen Rong. Damping Vibration Mechanism of the Elastic Bearing Block Track [J].Journal of the China Railway Society , 2007 ( 5) ; 69 -72.
[7]郭金玉,张忠彬,孙庆云.层次分析法的研究与应用 [J].中国安全科学学报,2008 (5 ) ;148-153.
Guo Jinyu, Zhang Zhongbin, Sun Qingyun. Study and Applications of Analytic Hierarch Process[J].China Safety Science Jouraaj > 20118 { 5) :148-153.
[8]徐雯,杨和礼.模糊决策在房地产建筑方案优选中的应 用[J].建筑管理现代化,2005(4);13-15.
Xu Wen, Yang Heli. Study on Application of Fuzzy Decision in Real Estate Plan Optimization Selection [ J ] . Construction Management Modernization, 2005(4): 13-15.
[9]张震,于天彪,梁宝珠,等.基于层次分析法与模糊综合评价的供应商评价研究[J].东北大学学报,2006 (10);1142-1145.
Zhang Zhen, Yu Tianbiao, Liang Baozhu, etc. AHP- Based vendor Evaluation in Combination with FCE仁J]. Journal of Northeastern University , 2006(10):1142- 1145.
[10]郑贤斌,李自力.油库安全综合评价的AHP - Fuzzy方 法[J].工业安全与环保,2004(2);43-45.
Zheng Xianbin , Li Zili. The AHP-Fuzzy Method for Comprehensive Evaluation of Oil Depot Safety[J]. Industrial Safety and Environmental Protection, 2004 (2);43-45.
|
|
|
|