|
|
Study on Three Line-transfer Programs in Hong Kong Road Station of Wuhan Rail Transit |
ZHAO Qiang |
China Railway Siyuan Survey and Design Group Co. Ltd,Wuhan,Hubei 430063 ,China |
|
|
Abstract Research purposes: There are large traffic flows on the Jianshe Avenue and Hong Kong road with many peripheral control factors. It is difficult to build a three line-transfer station in this area and also difficult to do the coordination work for construction. In order to avoid the impact of the track adjustment on the station,it is necessary to do the comprehensive research on the three line-transfer programs in the Hong Kong Road Station.
Research conclusions: Through the analysis of the functional orientation, transfer distance, passenger flow and distance between stations of each line,and based on working out and taking the countermeasures,the importance of the three line transfer was presented and the merits of centrally setting up stations for three lines was analyzed. In this way, the difficulties in construction and coordination were overcome,obtaining good results. The following conclusions are drawn: (1) The three line-transfer in Hong Kong Road Station is necessary because the Line 3,Line 6 and Line 7 meet here. (2) From the transfer function and the influence of station construction on surrounding environment, the central setting up station for 3 lines has certain advantages,but the attention should be paid to the positions of the escalators,exits and entrance to make the transfer passage smooth.
|
Received: 08 August 2012
|
|
|
|
|
[1] GB 50157—2003,地铁设计规范[S]. GB 50157—2003,Code for Design of Metro [S].
[2] 建标104-2008,城市轨道交通工程项目建设标准[S]. Jianbiao 104-2008,Urban Rail Transit Project Construction Standards [S].
[3] GB 50490—2009,城市轨道交通技术规范[S]. GB 50490—2009, Technical Code of Urban Rail Transit [S].
[4] GB/T 50546—2009,城市轨道交通线网规划编制标准[S]. GB/T 50546—2009, Code for Compilation of Urban Railway Network Planning [S].
[5] 中铁第四勘察设计院集团有限公司.武汉轨道交通3号线一期工程可行性研究报告[R].武汉:中铁第四勘察设计院集团有限公司,2011. China Railway Fourth Survey and Design Institute Group Co. Ltd. The Engineering Feasibility Study of Wuhan Rail Transit Line 3 [R]. Wuhan: China Railway Fourth Survey and Design Institute Group Co. Ltd, 2011.
[6] 中铁第四勘察设计院集团有限公司.武汉轨道交通3号线一期工程初步设计文件[Z].武汉:中铁第四勘察设计院集团有限公司,2012. China Railway Fourth Survey and Design Institute Group Co. Ltd. The Preliminary Design Documents of Wuhan Rail Transit Line 3 [Z]. Wuhan: China Railway Fourth Survey and Design Institute Group Co. Ltd, 2012.
[7] 朱丹,等.城市轨道交通工程概论[M].北京:人民交通出版社,2012. Zhu Dan, etc. Urban Rail Transit Project Introduction [M], Beijing: China Communications Press,2012.
[8] 毛保华.城市轨道交通[M].北京:科学出版社,2001. Mao Baohua. Urban Rail Transport [M]. Beijing: Science Press,2001.
[9] 胡双平.三线换乘车站换乘节点结构计算分析[J].铁道 工程学报,2011(10): 124-128. Hu Shuangping. Structural Calculation and Analysis of Transfer Node of Three-line Transfer Station [J]. Journal of Railway Engineering Society, 2011(10): 124-128.
|
|
|
|