|
|
Control,Test and Analysis of Soft Foundation of High - speed Railway |
LIAO Jin - xing |
China Railway Siyuan Survey and Design Group Co. Ltd,Wuhan,Hubei 430063,China |
|
|
Abstract Research purposes: The high - speed railway has a very strict requirement on the post - construction settlement of the foundation and the post - construction settlement of the foundation belongs to the residual settlement after rail laying. The appropriate calculation method for the foundation settlement should be chosen to satisfy the requirement of the post - construction settlement of high - speed railway,and the appropriate measures should be taken according to the calculation result of the settlement.
Research conclusions: The calculation thicknesses of the compression layer of the soft - soil high - compression foundation and the medium - compression clay foundation should be determined according to that the additional stress is equal to the 0. 1 time of its stress. The calculation thicknesses of the compression layer of the non - clay foundation and the low - compression clay foundation should be determined according to that the additional stress is equal to the 0. 2 time of its stress. The settlement in the reinforced range of the CFG pile composite foundation should be calculated by using the soil composite compression modulus method. When the settlement of the subjacent bed is calculated by using the equivalent entity method,its calculation result is rather closed to the real settlement. When the settlement in the reinforced range of the bored cast - in - place pile structure foundation is calculated with the pile theory and the settlement of the subjacent bed is calculated by using the stress diffusion method,their calculation results are rather closed to the measured settlement.
|
Received: 20 November 2012
|
|
|
|
|
[1] TB 10621—2009,高速铁路设计规范( 试行) [S].
TB 10621—2009,Code for Design of High Speed Railway [S].
[2] 郝瀛. 铁道工程[M]. 北京: 中国铁道出版社,2000.
Hao Ying. Railway Engineering [M]. Beijing: China Railway Publishing House,2000.
[3] 蔡英. 高速铁路路基研究[M]. 成都: 西南交通大学出版社,1995.
Cai Ying. Research of High Speed Railway Subgrade [M]. Chengdu: Southwest Jiaotong Universy Press, 1995.
[4] 郭光权. 客运专线路基沉降和变形监控[J]. 铁道工程学报,2007( 12) : 153 -157.
Guo Guangquan. Observation of Settlement and Deformation of Subgrade of Railway Passenger Dedicated Line [J]. Journal of Railway Engineering Society,2007( 12) : 153 - 157.
[5] 赵勇,陈占,徐红星. 高速铁路无砟轨道路基沉降监测和研究[J]. 铁道工程学报,2012( 6) : 45 -49.
Zhao Yong,Chen Zhan,Xu Hongxing. Control and Evaluation Method for Residual Settlement of High Speed Railway [J]. Journal of Railway Engineering Society,2012( 6) : 45 - 49.
[6] TB 10001—2005,铁路路基设计规范 [S].
TB 10001—2005, Code for Design on Subgrade of Railway[S].
[7] JGJ 79—2002,建筑地基基础设计规范[S].
JGJ 79—2002,Code for Design of Building Foundations [S].
[8] 顾湘生,赵新益,孙宏林,等. 软土地基路桥设计参数试验研究报告[R]. 武汉: 中铁第四勘察设计院集团有限公司,2005.
Gu Xiangsheng,Zhao Xinyi,Sun Honglin,etc. Test Study Report on Soft Soil Foundation Road & Bridge Design Parameters[R]. Wuhan: China Railway Siyuan Survey & Design Co. Ltd,2005.
[9] 陈占,陈远洪,汪莹鹤,等. 石武客运专线粉质土地基处理及工后沉降控制研究报告[R]. 武汉: 中铁第四勘察设计院集团有限公司,2012.
Chen Zhan,Chen Yuanhong,Wang Yinghe,etc. Report on Silty Soil Foundation Treatment and Residual Settlement Control of Shijiazhuang - Wuhan Passenger Dedicated Line[R]. Wuhan: China Railway Siyuan Survey & Design Co. Ltd,2012.
[10] 铁建设[2006]158 号,客运专线铁路无砟轨道铺设条件评估技术指南[S].
Railway Construction [2006 ] No. 158, Technical Guideline for Unballasted Track Laying Condition Assesment of Passenger Dedicated Railway Line[S].
[11] TB 10002. 5—2005,铁路桥涵地基和基础设计规范[S].
TB 10002. 5—2005,Code for Design on Subsoil and Foundation of Railway Bridge and Culvert [S].
|
|
|
|