Research on Construction Technology for Building Second Line Under Condition of Running EMU |
ZHAO Dai-qiang |
China Railway N0.8 Engineering Group Co. Ltd, Chengdu, Sichuan 610036, China |
|
|
Abstract Research purposes: In order to ensure the safety and quality of building the second-line of the Suining-Chongqing Railway under condition of running the EMU at speed of 165 km and the operation safety of the existing railway, it is necessary to do the study on the wind pressure influence when the EMU running and the key construction technologies of erecting the girder, laying track, welding unit and spreading and blocking the stress in the small midway between tracks of 4.4-6.5 m from the near existing track.
Research conclusions: (1)The analysis of wind pressure calculation of the EMU shows when the midway between tracks is 4.4m, the erecting equipment is in the stationary state and the speed of the EMU is at 165 km/h, the maximum amplitude of pressure fluctuation generated by the EMUs meeting is 637. 15 Pa and it is less than the allowable instantaneous pressure wave value of 900 Pa of the midway between tracks. The EMU's window structure and glass are in the safe and reliable state and the equipment has the high stability. (2)By adopting the method of blocking track for 5 hours to erect 1 beam or laying 300m long track panel, the laying and erecting works can be done in small midway between track of 4.4-6.5 m from the existing railway track. In this way, the construction safety and quality are guaranteed, the construction cost is cut and the construction period is shortened. (3)This research result can provide the reference to both small railway line spacing range of additional second-line construction technology.
|
Received: 17 June 2013
|
|
|
|
|
[1]熊小慧, 梁习锋. CRH2型动车组列车交会空气压力波试验分析[J].铁道学报,2009(6):15-20.
Xiong Xiaohui, Liang Xifeng. Air Pressure Wave Test and Analysis of Train CRH2 EMUS Rendezvous[J]. Journal of the China Railway Society, 2009(6):15-20.
[2]铁道部部令29号, 铁路技术管理规程[S].
MOR Order No.29, Regulations of Railway Technical Operation[S].
[3]成增胜.增建二线铁路铺架施工技术[J]. 铁道技术监督,2010(4):30-33.
Cheng Zengsheng. The Construction Technology of Railroad Line[J]. The Railway Technical Supervision, 2010(4):30-33.
[4]舒畅, 杨怀志. 既有铁路提速改造及增建二线单元式施工组织方法的应用[J]. 铁道工程学报,2005(4):69-72.
Shu Chang, Yang Huaizhi. The Speed-up Reconstruction of Existing Railway and the Application of Additional Second Unit Construction Organization Method[J]. Journal of Railway Engineering Society, 2005(4):69-72.
[5]铁建设[2006]181号, 铁路架桥机架梁暂行规程[S].
Railway Construction[2006] No.181, Railway Bridge Rack Beam Provisional Rules[S].
[6]TB/T 1632-1991, 钢轨焊接接头技术条件[S].
TB/T 1632-1991, Joint Technical Condition of Rail Welding [S].
|
|
|
|