Abstract Research purposes: In order to optimize the construction scheme and ensure the safety and operation of the existing station structure, the simulations were made for the construction schemes with the different excavation methods and for the different reinforcement ranges of the surrounding strata by using the analysis software with FLAC3D three-dimensional fast Lagrangian method according to the engineering characteristics of new tunnel under-passing the existing metro station at short range for the purposes of knowing the characteristics and laws of the existing station's track settlement and structure stress and the new tunnel's surrounding deformation and structure bearing load.
Research conclusions: (1) From the analysis and comparison of the calculations results of the excavation processes obtained by using method, the track the full section method, the bench method and CRD method, it is concluded by using the CRD deformation and structure bearing load of the existing station can be effectively controlled.(2)On the base of the analysis of the numerical simulation results of the different reinforcement ranges for the surrounding strata around the new tunnels, it is proposed the grouting reinforcement should be conducted to the soil sandwich layer, the working face layer and the layer within 3.0m range on the left and right sides of the tunnel. (3)This result can provide the reference to the design and construction of the similar tunnel under-passing the existing subway.
|
Received: 27 April 2013
|
|
|
|
|
[1]姚海波.大断面隧道浅埋暗挖法下穿既有地铁构筑物施工技术研究[D].北京:北京交通大学,2005.
Yao Haibo. Reseach on Construction Technology of Large Section Tunnel Crossing under the Existing Subway Tunnel by Means of Shallow Tunneling Method[D]. Beijing: Beijing Jiaotong University, 2005.
[2]张成满, 罗富荣.地铁工程建设中的环境安全风险技术管理体系[J].都市快轨交通, 2007(12):63-65.
Zhang Chengman, Luo Furong, Technical Management System of Environmental Safety Risk for Metro Construction[J]. Urban Rapid Rail Transit, 2007(12):63-65.
[3]张成平, 张顶立, 吴介普, 等.暗挖地铁车站下穿既有地铁隧道施工控制[J].中国铁道科学,2009(1):69-73.
Zhang Chengping, Zhang Dingli, Wu Jiepu, etc. Construction Control of a Newly-Built Subway Station Undercrossing the Eaasting Subway Tunnel[J]. China Railway Science, 2009(1):69-73.
[4]张成平, 张顶立, 骆建军, 等.地铁车站下穿既有线隧道施工中的远程监测系统[J].岩土力学, 2009(6):1861-1866.
Zhang Chengping, Zhang Dingli, Luo Jianjun, etc. Remote Monitoring System Applied to the Construction of Metro Station Undercrossing Eansting Metro Tunnel[J]. Rock and Soil Mechanics, 2009(6):1861-1866.
[5]赵东平.小净距平行隧道下穿施工对多层建筑的影响研究[J].现代隧道技术, 2011(5):30-38.
Zhao Dongping. The Effects of Parallel Tunnel Construction with a Small Clear Distance on a Multistory Building[J]. Modern Tunneling Technology, 2011(5):30-38.
[6]魏家君.隧道下穿暗河施工技术[J].铁道工程学报, 2007(7):71-75.
Wei Jiajun. Construction Technology for Tunnel Underpassed Underground River[J]. Journal of Railway Engineering Society, 2007 (7):71-75.
[7]李东海, 刘军, 萧岩, 等.盾构隧道斜交下穿地铁车站的影响与监测研究仁J].岩石力学与工程学报, 2009(S1):3186-3192.
Li Donghai, Liu Jun, Xiao Yan. Research on Influence and Monitoring of Shield Tunnel Obliquely Crossing Beneath Existing Subway Station[J]. Chinese Journal of Rock Mechanics and Engineering, 2009,28(S1):3186-3192.
[8]房倩, 张顶立.浅埋暗挖地铁车站下穿既有线结构施工方法研究[J].中国铁道科学, 2007(5):71-77.
Fang Qian, Zhang Dingli. Study on the Shallow Tunnel Construction Methods for a Newly-Built Subway Station Passing through the Bottom of the Existing Subway[J]. China Railway Science, 2007(5):71-77.
[9]张印涛, 陶连金, 张飞劲, 等.矿山法开挖近距离下穿越既有线隧道的三维数值模拟[J].北京工业大学学报, 2007(12):1273-1277.
Zhang Yintao, Tao Lianjin, Zhang Jinfei. Numerical Modeling of Tunneling Cross Under Ultra-near Metro Tunnel[J]. Journal of Beijing University of Technology, 2007(12):1273-1277.
[10]韩煊, 刘赦炜, Jamie R. Standing.隧道下穿既有线的案例分析与沉降分析方法[J].土木工程学报, 2012(1):134-141.
Han Xuan, Liu Chengwei, Jamie R. Standing. Structural Settlement of Existing Tunnel Caused by New Tunnel Excavated Underneath[J]. China Civil Engineering Journal, 2012(1):134-141.
[11]陈孟乔, 杨广武.新建地铁车站近距离穿越既有地铁隧道的变形控制[J].中国铁道科学, 2011(4):53-59.
Chen Mengqiao, Yang Guangwu. Deformation Control of a Newly-Built Subway Station Crossing the Adjacent Existing Subway Tunnel[J]. China Railway Science, 2011(4):53-59.
[12]常翔.地铁车站近接正交下穿既有地铁隧道的变形分析[J].现代隧道技术,2011(3):69-73.
Chang Xiang. Deformation Analysis of the Subway Station Perpendicularly Under-passing an Existing Subway Tunnel with a Small Clear Distance[J]. Modern Tunneling Technology, 2011(3):69-73.
|
|
|
|