Research on Adjustments of Track and Gradient of Line 2 of Wuhan Metro |
ZHAO Qiang |
China Railway Siyuan Survey and Design Group Co. Ltd,Wuhan,Hubei 430063,China |
|
|
Abstract Research purposes: Adjustments of track and gradient are the comprehensive multi-disciplinary work,and its purpose are to eliminate the gaps,the mistakes,the missing and the other errors produced in metro construction by adjustment of track plane and vertical section to make the track meeting the various boundary requirements of the devices. Whether the metro station and the interval structure invade the boundary or not is crucial to the metro. As the work to examine and eliminate the invasion of the boundary,the adjustment of track and gradient has become an indispensable work. Compared with the actual project,this paper sums up the design process of the adjustments of track and gradient and the problems encountered in it for giving a hand to metro design and construction.
Research conclusions : From the research it is concluded:(1)It is easy to control the construction precision of open cut structure. If any part of it invades the boundary,the treatment can be conducted to the structure to make it meeting the requirements. (2)During shield construction,if the shield invades the boundary due to no effective control of gesture, the slow correction should be made and after it the conditions for the adjustments of track and gradient can be realized. (3)The section measurement should be conducted tensely to the sharp change areas of the station or the interval structure to avoid missing the boundary control point.(4)The attention should be paid to the relation between the track structure and the drainage pipe in the lowest area.(5)The track design should comprehensively consider the EIA requirements.
|
Received: 10 March 2013
|
|
|
|
|
[1]GB 50157—2003,地铁设计规范[S].
GB 50157—2003 , Code for Design of Metro [ S ].
[2]建标104—2008,城市轨道交通工程项目建设标准[S].
Jianbiao 104—2008,Urban Rail Transit Project Construction Standards[S].
[3]GB 50490—2009,城市轨道交通技术规范[S].
GB 50490—2009 , Technical Code of Urban Rail Transit [S].
[4]GB 50308—2008,城市轨道交通工程测量规范[S].
GB 50308—2008,Code for Urban Rail Transit Engineering Survey [S ].
[5]中铁第四勘察设计院集团有限公司.武汉轨道交通2号线一期工程施工图设计文件[Z].武汉:中铁第四勘察设计院集团有限公司,2011.
China Railway Fourth Survey and Design Institute Group Co. Ltd. The Construction Detail Design Documents of Wuhan Rail Transit Line 2 [Z] .Wuhan: China Railway Fourth Survey and Design Institute Group Co. Ltd, 2011.
[6]马振海.地铁主体结构变形监测的必要性分析[J],铁道工程学报,2008(8):93 - 95.
Ma Zhenhai. Analysis of Necessity of the Primary Structural Transmutation Observation in Subways [J]. Journal of Railway Engineering Society , 2008(8):93- 95.
[7]毛保华.城市轨道交通[M].北京:科学出版社,2001.
Mao Baohua. Urban Rail Transport[M].Beijing : Science Press , 2001.
[8]何晓辉.地铁测量控制要点[J].隧道建设,2007 ( 4 ): 72-73.
He Xiaohui. Control Essentials of Metro Survey[J]. Tunnel Construction , 2007 ( 4 ) :72-73.
|
|
|
|