Study on Reasonable Slope Shape of Temporary Slope in Open Cut Area of Loess Tunnel |
CHENG Wen – bin1, JIANG Xin - zhao2 |
1. China Railway No.3 Engineering Group Co. Ltd, Taiyuan, Shanxi 030006, China;2. China University of Mining And Technology( Beijing) , Beijing 100083, China |
|
|
Abstract Research purposes: In order to ensure the slope safety during excavation under the condition of no supporting, save the cost and prevent the slope collapse, the reasonable excavation slope shape should be selected for the temporary slope in the open cut exit of the Hanguguan Tunnel of the Zhengzhou - Xian High - speed Railway.
Research conclusions : By doing the numerical calculation,the analyses of the stress change regulation and the influence of the slope shape on the loess slope stability were made to monitor the displacement variation characteristics of the empty surface and internal parts of the slope body. The result showed : (1) The upright side wall was harmful to the slope stability, and the maximum displacement appeared on the top of the upright side wall. (2) The overall stability of the slope with the upright sidewall is not only affected by the slope of the excavation depth,but also by the slope ratio of the secondary slope adjacent to upright sidewall. When the slope excavation depths were the same, the small the slope ratio of secondary slope was and the better the overall stability of the excavation slope was. (3) To ensure the excavation safety of the temporary loess slope in the open cut exit of the Hanguguan Tunnel of the Zhengzhou – Xi′ an High — speed Railway, the straight slope was used, with the upright sidewall height of 9 m and the secondary slope ratio of 1 : 1. The research results can provide the scientific basis for the similar works.
|
Received: 21 January 2013
|
|
|
|
|
[1]中铁三局集团有限公司,西南交通大学.郑西客运专线黄 土高陡边坡变形机理及施工关键技术研究[R].太原:中 铁三局集团有限公司,西南交通大学,2009.
The Third Engineering Group Co. Ltd. of China Railway, Southwest Jiaotong University. Deformation Mechanism and Key Construction Technology Research on Loess High Slope in Zhengzhou - Xi an Passenger Dedicated Line [ R ] ? Taiyuan : The Third Engineering Group Co. Ltd. of China Railway, Southwest Jiaotong University, 2009.
[2]王念秦,罗东海,姚勇.铁路黄土高边坡变形破坏机理及 稳定性研究[J].铁道工程学报,2009(7) :10-14.
Wang Nianqin, Luo Donghai , Yao Yong. Research on the Deformation Failure Mechanism and Stability of High Loess Slope along Railway [J ] .Journal of Railway Engineering Society, 2009(7) :10 -14.
[3]伍俊,郑全平.复合土钉支护技术的有限元数值模拟及工程应用[J].岩土工程学报,2005(4) :388 -392.
Wu Jun,Zheng Quanping. Numerical Simulation in Finite Element and Engineering Application of Compound Soil Nail Support Technology [ J ] .Chinese Jounal of Geotechnlcal Engineering,2005 ( 4) : 388 -392.
[4]于国新.黄土及其边坡稳定的一些探讨[J].铁道工程学 报,2011(6) :1-4.
Yu Guoxin. Exploration on the Loess and the Stability of Slope [ J ] .Journal of Railway Engineering Society, 2011(6): 1-4.
|
|
|
|